All scaffolding erected, altered, or dismantled on behalf of Zuno must:
Installation Requirements
Ground & Structural Requirements
Inspection Requirements
Contractor must:
Additional Responsibilities
Contractor is responsible for:
Operational Timescales
Activity
Requirement
Job issued by Zuno
Minimum 5 working days before installation
Customer contacted
3 working days before erection
Scaffold erection
Normally 2 working days before solar installation
Scaffold dismantle
Within 2 working days after installation completion
Upload photos & documentation
Within 24 hours
Retain photographs
30 days
Required photographs:
Schedule of Rates (Excluding VAT)
Property
1 face
2 face
3 face
1 storey
£500
£700
£950
2 storey
£550
£750
£1,050
3 storey
£750
£1,150
£1,650
Supplier KPIs
Activity
TARGET
Job acknowledgement
Within 1 working day
Handover pack
Within 1 working day after scaffold erection
Damage reporting
Within 24 hours
Scaffold dismantling
Within 2 working days of expected Solar PV completion
Commercial Notes
Contractor Recharges & Service Credits
To ensure consistent service delivery and minimise disruption to customers, Zuno reserves the right to apply financial recharges where a Supplier fails to meet the requirements of this Agreement. These recharges are intended to recover costs incurred by Zuno, including customer compensation payments, additional administration, and Job Gone Down (JGD) charges payable to installation teams.
1. Scaffold No-Show
Where a Supplier accepts a scaffold order and fails to attend on the agreed erection date without prior approval from Zuno, a recharge of £100 per occurrence will be applied.
This recharge reflects the costs associated with:
2. Late Erection
Where scaffolding is not erected within the agreed Service Level Agreement (SLA), resulting in delays to the planned solar installation, Zuno reserves the right to recover all reasonable costs incurred, including:
In addition, Zuno may apply a fixed service credit of £100 where the delay is solely attributable to the Supplier.
3. Failure to Dismantle Within SLA
Scaffolding must be dismantled within 2 working days of the confirmed completion of the solar installation unless otherwise agreed.
Failure to meet this requirement may result in:
4. Compliance & Quality Failures
Where scaffolding is found to be non-compliant with TG20:21, Working at Height Regulations, manufacturer guidance, or Zuno's installation requirements, the Supplier may be liable for all associated costs.
Examples include (but are not limited to):
Where a compliance or quality issue prevents the installation from proceeding, Zuno may recover:
A fixed recharge of up to £100 per occurrence may also be applied depending on the severity of the non-compliance.
5. Failure to Upload Documentation
The Supplier is required to upload all required photographs, handover documentation and supporting information within the agreed timescales.
Failure to provide:
within 24 hours may result in a recharge of £25 per occurrence.
6. Repeated Performance Issues
Where a Supplier demonstrates repeated failures to meet Zuno's quality standards or SLA requirements, Zuno reserves the right to:
General
All recharges will be reviewed on a case-by-case basis and will be supported by appropriate evidence, including photographs, installation records, customer correspondence, engineer reports and app data.
Where multiple failures arise from a single event, Zuno reserves the right to recover the full cost incurred where these exceed the standard recharge values listed above.
All scaffolding erected, altered, or dismantled on behalf of Zuno must:
Installation Requirements
Ground & Structural Requirements
Inspection Requirements
Contractor must:
Additional Responsibilities
Contractor is responsible for:
Operational Timescales
Activity
Requirement
Job issued by Zuno
Minimum 5 working days before installation
Customer contacted
3 working days before erection
Scaffold erection
Normally 2 working days before solar installation
Scaffold dismantle
Within 2 working days after installation completion
Upload photos & documentation
Within 24 hours
Retain photographs
30 days
Required photographs:
Schedule of Rates (Excluding VAT)
Property
1 face
2 face
3 face
1 storey
£500
£700
£950
2 storey
£550
£750
£1,050
3 storey
£750
£1,150
£1,650
Supplier KPIs
Activity
TARGET
Job acknowledgement
Within 1 working day
Handover pack
Within 1 working day after scaffold erection
Damage reporting
Within 24 hours
Scaffold dismantling
Within 2 working days of expected Solar PV completion
Commercial Notes
Contractor Recharges & Service Credits
To ensure consistent service delivery and minimise disruption to customers, Zuno reserves the right to apply financial recharges where a Supplier fails to meet the requirements of this Agreement. These recharges are intended to recover costs incurred by Zuno, including customer compensation payments, additional administration, and Job Gone Down (JGD) charges payable to installation teams.
1. Scaffold No-Show
Where a Supplier accepts a scaffold order and fails to attend on the agreed erection date without prior approval from Zuno, a recharge of £100 per occurrence will be applied.
This recharge reflects the costs associated with:
2. Late Erection
Where scaffolding is not erected within the agreed Service Level Agreement (SLA), resulting in delays to the planned solar installation, Zuno reserves the right to recover all reasonable costs incurred, including:
In addition, Zuno may apply a fixed service credit of £100 where the delay is solely attributable to the Supplier.
3. Failure to Dismantle Within SLA
Scaffolding must be dismantled within 2 working days of the confirmed completion of the solar installation unless otherwise agreed.
Failure to meet this requirement may result in:
4. Compliance & Quality Failures
Where scaffolding is found to be non-compliant with TG20:21, Working at Height Regulations, manufacturer guidance, or Zuno's installation requirements, the Supplier may be liable for all associated costs.
Examples include (but are not limited to):
Where a compliance or quality issue prevents the installation from proceeding, Zuno may recover:
A fixed recharge of up to £100 per occurrence may also be applied depending on the severity of the non-compliance.
5. Failure to Upload Documentation
The Supplier is required to upload all required photographs, handover documentation and supporting information within the agreed timescales.
Failure to provide:
within 24 hours may result in a recharge of £25 per occurrence.
6. Repeated Performance Issues
Where a Supplier demonstrates repeated failures to meet Zuno's quality standards or SLA requirements, Zuno reserves the right to:
General
All recharges will be reviewed on a case-by-case basis and will be supported by appropriate evidence, including photographs, installation records, customer correspondence, engineer reports and app data.
Where multiple failures arise from a single event, Zuno reserves the right to recover the full cost incurred where these exceed the standard recharge values listed above.
All scaffolding erected, altered, or dismantled on behalf of Zuno must:
Installation Requirements
Ground & Structural Requirements
Inspection Requirements
Contractor must:
Additional Responsibilities
Contractor is responsible for:
Operational Timescales
Activity
Requirement
Job issued by Zuno
Minimum 5 working days before installation
Customer contacted
3 working days before erection
Scaffold erection
Normally 2 working days before solar installation
Scaffold dismantle
Within 2 working days after installation completion
Upload photos & documentation
Within 24 hours
Retain photographs
30 days
Required photographs:
Schedule of Rates (Excluding VAT)
Property
1 face
2 face
3 face
1 storey
£500
£700
£950
2 storey
£550
£750
£1,050
3 storey
£750
£1,150
£1,650
Supplier KPIs
Activity
TARGET
Job acknowledgement
Within 1 working day
Handover pack
Within 1 working day after scaffold erection
Damage reporting
Within 24 hours
Scaffold dismantling
Within 2 working days of expected Solar PV completion
Commercial Notes
Contractor Recharges & Service Credits
To ensure consistent service delivery and minimise disruption to customers, Zuno reserves the right to apply financial recharges where a Supplier fails to meet the requirements of this Agreement. These recharges are intended to recover costs incurred by Zuno, including customer compensation payments, additional administration, and Job Gone Down (JGD) charges payable to installation teams.
1. Scaffold No-Show
Where a Supplier accepts a scaffold order and fails to attend on the agreed erection date without prior approval from Zuno, a recharge of £100 per occurrence will be applied.
This recharge reflects the costs associated with:
2. Late Erection
Where scaffolding is not erected within the agreed Service Level Agreement (SLA), resulting in delays to the planned solar installation, Zuno reserves the right to recover all reasonable costs incurred, including:
In addition, Zuno may apply a fixed service credit of £100 where the delay is solely attributable to the Supplier.
3. Failure to Dismantle Within SLA
Scaffolding must be dismantled within 2 working days of the confirmed completion of the solar installation unless otherwise agreed.
Failure to meet this requirement may result in:
4. Compliance & Quality Failures
Where scaffolding is found to be non-compliant with TG20:21, Working at Height Regulations, manufacturer guidance, or Zuno's installation requirements, the Supplier may be liable for all associated costs.
Examples include (but are not limited to):
Where a compliance or quality issue prevents the installation from proceeding, Zuno may recover:
A fixed recharge of up to £100 per occurrence may also be applied depending on the severity of the non-compliance.
5. Failure to Upload Documentation
The Supplier is required to upload all required photographs, handover documentation and supporting information within the agreed timescales.
Failure to provide:
within 24 hours may result in a recharge of £25 per occurrence.
6. Repeated Performance Issues
Where a Supplier demonstrates repeated failures to meet Zuno's quality standards or SLA requirements, Zuno reserves the right to:
General
All recharges will be reviewed on a case-by-case basis and will be supported by appropriate evidence, including photographs, installation records, customer correspondence, engineer reports and app data.
Where multiple failures arise from a single event, Zuno reserves the right to recover the full cost incurred where these exceed the standard recharge values listed above.